10 Feb 2021 | 11:07 AM UTC
South Africa: Utility provider Eskom announces load shedding Feb. 10-11
South Africa's utility provider, Eskom, has announced Stage-3 load shedding from 1300 Feb. 10 to 0600 Feb. 11.
Event
South African utility provider Eskom has announced that Stage-3 load shedding will be implemented nationwide from 1300 Feb. 10 through to 0600 Feb. 11. Eskom has stated that this is necessary due to the severe strain on the power generation system as a result of high-generation unit breakdowns during the past three days.
Temporary commercial and communications disruptions are possible while the load shedding is taking place; cellular and mobile services could be affected. Traffic disruptions and longer driving times are possible during these periods due to malfunctioning traffic signals. Trains may also experience delays if outages impact signaling devices or overhead wires. Power outages could also result in the temporary unavailability of essential services such as ATMs and filling stations. There is an increased security threat during power outages. Blackouts could adversely affect security protocols, including alarm systems and electronic fences; opportunistic criminal activity could increase during electricity outages.
Context
Load shedding requires switching off parts of South Africa's electric grid in a planned and controlled manner due to insufficient capacity or to avoid a countrywide blackout.
Stage-1 load shedding: Allows for up to 1,000MW of electricity to be removed from the power grid, leading to power supply cuts in the impacted area three times over a four-day period for two hours at a time, or three times over an eight-day period for four hours at a time.
Stage-2 load shedding: Allows for up to 2,000MW of electricity to be removed from the power grid, leading to power supply cuts in the impacted area six times over a four-day period for two hours at a time, or six times over an eight-day period for four hours at a time.
Stage-3 load shedding: Allows for up to 3,000MW of electricity to be removed from the power grid, leading to power supply cuts in the impacted area nine times over a four-day period for two hours at a time, or nine times over an eight-day period for four hours at a time.
Stage-4 load shedding: Allows for up to 4,000MW to be removed from the power grid, leading to power supply cuts in the impacted area 12 times over a four-day period for two hours at a time, or 12 times over an eight-day period for four hours at a time.
Authorities in the City of Cape Town are likely to continue to implement support measures and supply electricity during load shedding periods. Typically, city supply will move the stage down one level from the Eskom-announced load shedding level.
Advice
Plan for electricity disruptions. Conserve batteries and restrict cellphone use to emergencies in case of an extended power outage. For safety reasons, monitor generators while they are operating due to potential fires. Unplug appliances and electronic equipment to protect against surge damage when power resumes.
Resources
Eskom load-shedding schedules
Eskom (Twitter)
City of Cape Town (Twitter)
City of Tshwane (Twitter)
City of Johannesburg (Twitter)